Friday, February 29, 2008

Concrete

Views of pouring the concrete for the footings and piers in the basement of the Annex building.

Details (image numbers in parentheses):
A conveyor truck was used to move the concrete from the ready mix trucks to the forms (010, 015). The conveyor truck driver uses a remote control device to maneuver the extension arm into the correct position over the wooden form. The workers in the foundation site guide the
rubber chute at the end of the arm and spread and level the concrete within the form (019, 024). Later steel reinforcing rods are set into the concrete to strengthen the walls that will be built on top of the footings. In each of the isolated piers, four anchor bolts are set. When the steel columns are erected, their bases are anchored down by these bolts with washers and nuts (027). Samples of concrete are taken and tested to ensure that the concrete mix is of the right consistency and will attain its specified strength at the end of its 28 day curing period (016, 021).

Monday, weather permitting, block work for the west, south and north walls will begin. Then later next week, the east wall will be formed up and concrete poured into the forms. In the following week the plumber and the electrician will install their pipes and cables before the
concrete floor of the lower level is poured. ~ DS

Concrete (Photo #10)

Concrete (Photo #15)

Concrete (Photo #16)

Concrete (Photo #19)

Concrete (Photo #21)

Concrete (Photo #24)

(Photo #27)

Thursday, February 28, 2008

Details of Foundation Form Work

The second day of form work is completed. Concrete is scheduled to be poured on Friday, Feb 29th.

~ DS

Postscript: Following are descriptions and details for those among us who are interested in how buildings are put together.

Details: Notice the steel reinforcing bars set within the wood forms. The re-bars sit above the stone base upon small metal frames called chairs (first two pictures). The chairs assure that when the concrete is poured into the forms, the concrete will flow around and under the re-bars. Re-bars are used to reinforce the concrete, reducing cracking and improving the distribution of the building loads. In the isolated piers (third picture) the re-bar is criss-crossed and wired together to form a mat which sits on the chairs. Again, the concrete when poured entirely surrounds the steel.

Side note for trivia addicts: For those of you who have traveled to Cape May, New Jersey, you may have seen the remains of the SS Atlantis, a concrete ship just off shore at Sunset Beach. It was one of twelve experimental concrete merchant ships built during the closing days of WWI, when steel was scarce. Eventually, it was decommissioned and was to be used as a break water at the Cape May ferry, but the Atlantis broke loose in a storm and ran aground. This ship was built using steel reinforced (ferro-cement) construction, much like the footing system seen in the photos below.

But sorry, our new building won't float.

Details of foundation form work of Annex building (east wall footing looking north from location of rm117)

Details of foundation form work of Annex building (looking NE from east wall of rm 105, exterior stairway surround)

Details of foundation form work of Annex building (isolated pier footing)


Details of foundation form work of Annex building (from NW corner looking west, exterior stair of rm 105 in foreground)

Details of foundation form work of Annex building (looking due south from foyer, rm 110, to pierD1, rm 113, west wall of rm 114, sw corner)

Wednesday, February 27, 2008

Forms for the Footings

Today the form work for the concrete footings began. The footings support the walls of the lower level which in turn suport everything above them. Within the outline of the footings you will notice additional forms. These are for the concrete bases of the steel columns which will support the floors above. All of this work sits on top of the compacted stone base. Even though we have had rain and snow and the soil around the work site is a soft muddy muck which is hard even to walk in, the stone base remains dry and firm allowing work to continue. ~ DS




Thursday, February 21, 2008

Shades of Mike Mulligan

Views of the work on day three as the foundation excavation continues. There now is so much dirt removed from the hole that the excavator has to load it into a truck and dump it at the far end of the work area.

The track hoe (power excavator) has reached the north east corner of the foundation hole and is moving towards the north west corner. The south east and south west corners were reached Tuesday and Wednesday respectively.

Note the continuing placement of the geotextile fabric and the 16" layer of crushed stone placed on top of it.

Once this stage is completed, the concrete contractor can start his work pouring the footings.

~ DS

Postscript: Parents of young children might want to put Mike Mulligan and His Steam Shovel into the bedtime reading rotation about now.





Tuesday, February 19, 2008

A Hole Is To Dig



We have a hole in the ground and a nice new sign to explain what it's for.

~ DS